How do I get a gas permit for my home?
Obtaining an gas permit to perform work on your own
home is a pretty easy process, but there are a few
basics that must be covered before a permit is issued:
- First, do you own the property? If you don't own
the property, we can't issue you a permit.
- Second, is this your primary residence? Florida
Statutes only allow us to issue a property owner
a permit if they reside in the dwelling. Because
a landlord doesn't live in rental property, he or
she may not pull a permit to perform their own work
on that property.
- Third, will you be doing the work yourself? In
order to get a permit, you have to actually perform
the work yourself. If you have to hire someone to
do the work, why would you hire someone who isn't
licensed to do it?
- Fourth, do you have the knowledge to do this
gas work safely and effectively? To ensure your
safety and that the quality of your work will meet
the gas code, we'll give you a short verbal test
We will also ask you to draw a diagram showing your
project and ask you to explain it to us.
You'll
need to meet with an inspector between 7:30 and 8:30
in the morning to go over these questions. When the
inspector is satisfied that you know what you're doing,
he/she will sign off on your application and you will
be allowed to obtain a permit.
The Gas Permit Process
First, post your permit card on the site and perform
the "rough" work associated with the gas
installation. This means that all piping should be
installed, secured and strapped, and that there are
no leaks.
The day before you are ready for it, call for your
"rough" inspection. The inspector must be
able to see the entire installation, so make sure
that you haven't installed insulation or sheetrock
and if there is any slab or ditch work, that it remains
uncovered.*
When the inspector completes the "rough"
inspection, he/she will either sign the posted permit
card or leave a "rough" sticker on the piping
at the gas meter location or other location on the
job site. If he/she finds a discrepancy, he/she will
call you to tell you what was found.
Complete the installation including wall finishes
and gas appliances. When this is complete, call for
your "final" inspection.
If your gas installation complies with code, the inspector
will pass the inspection and a white sticker will
be placed on the piping at the gas meter location.
NOTE: Connection to electrical power will be delayed
until the electrical, plumbing, gas, mechanical, and
building inspections have all been passed and the
inspection paperwork is assembled in our office. As
soon as possible, we will forward the permit number,
as approved, to the power company. Normally, new services
are connected in 2-3 days if no line work is required.
It is your responsibility to open an account with
your water company, and provide them with a deposit
(if required), billing information, and your permit
number.
Also, before you request a "rough" framing
inspection, you must have passed your electrical,
plumbing, gas, and mechanical inspections.
* If the inspector is unable to examine the entire
installation, he/she will have to return at a later
date. You will then be charged a reinspection fee
as well as having to remove any materials that obscure
the site. You're also responsible for ensuring the
inspector has access to the premises. Again, if the
inspector can't get to the installation, you will
be charged a reinspection fee.
|